The transformations in this global job are used for the most part to import views from the source data pool and schema/s. These views are mostly the same, however sometimes quantity and currency conversions are performed here. See the information for Global Job 3.0 description for more information. 

Create View: _CEL_PP_ACTIVITIES

This transformation is used to create a view from the PP activities table. The most important activities in this eventlog for this data model is the Actual Start Time and the Actual Finish Time. If the PP process is being set up specifically for the Inventory Management App, then those are the two activities that should be validated with priority. The app will still function if only those two activities are present in the PP eventlog.